Module 6: Implementation
Lesson 2 of 3
18 min

Launching ARTs

Practical guidance for organizing, preparing, and running your first ART.

1Organizing the ART

Before your first PI Planning, you need to define the ART's structure:

1. Define the value stream: What value does this ART deliver? To whom? Be specific. "We build the customer-facing web and mobile applications" is better than "We do frontend."

2. Identify the people: Who will be on the ART? This often means pulling people from existing teams and reorganizing them. Target 50-125 people. Include all skills needed for end-to-end delivery.

3. Form the teams: Create cross-functional teams of 5-11 people. Optimize for:

  • Minimize dependencies between teams
  • Maximize each team's ability to deliver end-to-end value
  • Balance skills and experience across teams
  • Respect existing relationships and working patterns where possible

4. Assign ART roles:

  • RTE: Your best facilitator with systems-thinking ability. This role makes or breaks the ART.
  • Product Management: Someone who deeply understands customer needs and can prioritize ruthlessly.
  • System Architect: Your most respected technical leader who thinks about the whole system.

5. Define the cadence:

  • Iteration length: 2 weeks (default, adjust only if you have strong reasons)
  • PI length: 5 iterations + 1 IP iteration = 12 weeks (default)
  • PI Planning: 2 days, face-to-face

Common organizing mistakes:

  • Creating teams by technology layer (frontend team, backend team, database team) instead of by feature area
  • Assigning the RTE role to a project manager who hasn't been trained
  • Making Product Management a committee instead of a person
  • Splitting people across multiple ARTs

Feature Teams Over Component Teams

Feature teams (full-stack, delivering end-to-end) outperform component teams (specialized by layer) at scale. Component teams create handoff dependencies. Feature teams can deliver independently.

2Preparing for First PI Planning

The first PI Planning is the ART's launch event. Preparation is critical:

8 weeks before:

  • Assign and train the RTE, Product Management, and System Architect
  • These roles need SAFe-specific training (Leading SAFe, SAFe for Architects, etc.)
  • Begin building the Program Backlog with 8-12 features for the first PI

6 weeks before:

  • Train all team members (SAFe for Teams training, 2 days)
  • Form the teams and assign Scrum Masters and Product Owners
  • Set up the development infrastructure (repos, CI/CD, environments)

4 weeks before:

  • Prepare the business context presentation (executive sponsor)
  • Prepare the product/solution vision presentation (Product Management)
  • Prepare the architecture vision presentation (System Architect)
  • Refine the top Program Backlog features (acceptance criteria, sizing)

2 weeks before:

  • Logistics: Book the room (big enough for all teams), prepare materials (boards, stickies, string), set up A/V
  • Communication: Send agenda, expectations, and pre-reading to all attendees
  • Dry run: RTE, PM, and SA rehearse their presentations
  • Backlog readiness: Top 10-15 features are refined and ready for team decomposition

Day before:

  • Set up the room. Each team gets a table/area. Program board is on the wall. Presentations are loaded and tested.
  • RTE does a final walkthrough of the agenda and logistics.

Key success factor: Don't try to get the first PI Planning perfect. It will be messy. The goal is to plan together, surface dependencies, and create alignment—not to produce a flawless plan. Perfection comes with practice.

3The First Few PIs

The first PI is about learning the mechanics. Don't judge the ART's performance by PI 1 results.

PI 1 — Learning the Dance

  • Teams are learning new processes and roles
  • PI Planning feels chaotic and runs over time
  • Too many dependencies are discovered—this is good (they existed before, you just couldn't see them)
  • Predictability is low (50-70% of planned objectives delivered is normal)
  • Focus: Get the cadence right. Run all events. Learn from each one.

PI 2 — Finding the Rhythm

  • PI Planning is smoother (teams know what to expect)
  • Dependencies are better managed (some have been eliminated)
  • Predictability improves (60-80%)
  • Teams start self-organizing more effectively
  • Focus: Improve quality practices. Start addressing systemic impediments from I&A.

PI 3 — Hitting Stride

  • The cadence feels natural
  • Predictability stabilizes (80%+)
  • Cross-team collaboration improves (trust builds through repeated interaction)
  • ART-level metrics become meaningful (trend data)
  • Focus: Optimize flow. Reduce batch sizes. Address architectural constraints.

PI 4+ — Continuous Improvement

  • The ART is a performing team of teams
  • Improvement is incremental and data-driven
  • The I&A process produces impactful changes
  • Focus: Performance optimization. Innovation. Helping other ARTs learn from your experience.

The coach's role: Lean-Agile coaches should be embedded with the ART for the first 3-4 PIs. They coach RTEs, Scrum Masters, Product Owners, and leadership. Gradually reduce coaching intensity as competence builds. Don't remove coaching too early—regression is common.

Premature Optimization

Don't customize SAFe in PI 1. Run it by the book first. You can't effectively adapt a process you haven't yet experienced. Wait until PI 3-4 to start tailoring practices based on empirical evidence.

Key Takeaways
  • Form feature teams of 5-11 people; minimize cross-team dependencies
  • Start PI Planning preparation 8 weeks before the event
  • Expect 3 PIs to reach steady-state performance
  • Run SAFe by the book first; customize based on experience, not theory